|
 |
|
Introduction
Hartwell Dam and Lake was the U.S. Army Corps of
Engineers second multipurpose “project” in the Savannah River Basin.
Authorized by Congress under the Flood Control Act of 1950, the Hartwell
Project was built between 1955 – 1962 for the purposes of hydropower,
flood control, and downstream navigation. Additional purposes of the
project now include water supply, water quality, recreation, and fish
and wildlife management. Filling of the lake began in February 1961 and
was completed in March 1962. The powerplant first went on-line in April
1962.
The powerplant originally consisted of four generators with provisions
made for a 5th generator based on the foresight that additional power
demands would be likely. The 5th generator was installed in 1983. The
powerplant at the Hartwell Project has the distinction of being the only
hydroelectric plant to be totally designed and constructed by the Corps
with the generators located outdoors.
Hartwell Dam is a concrete-gravity structure flanked on both sides by
embankments of compacted earth. The concrete section is 1,900 feet long
and rises 204 feet above the riverbed at its highest point. The earthen
embankments on each side of the dam lengthen it to over 3 miles. The dam
creates a 55,900-acre lake that stretches 49 miles up the Tugaloo River
and 45 miles up the Seneca River. These two rivers – the Tugaloo and
Seneca – come together to create the Savannah River, 7.1 miles above the
Hartwell Dam.
The dam is located approximately 300 river miles above the mouth of the
Savannah River where it empties into the Atlantic Ocean (in Savannah,
Georgia) and 90 miles above Augusta, Georgia. Two other Corps projects –
J. Strom Thurmond (formerly Clarks Hill) located near Augusta (completed
in 1954), and Richard B. Russell, located between Hartwell and Thurmond
Projects near Elberton, Georgia (completed in 1985) – join Hartwell to
form a chain of lakes 120 miles long.
The Corps of Engineers is the nation’s leading producer of hydroelectric
energy and Hartwell Dam and Powerplant is part of the Corps’ national
commitment to this energy. Hydroelectric power generation continues to
be the only pollution-free means of producing commercial energy.
Hydropower Generation
Hartwell Powerplant is referred to as a “peaking” plant
– which means the powerplant is designed to supply dependable power
during hours of “peak” daily demand. In addition to being a very clean
energy source, another major advantage of hydropower is the availability
to come “on-line” (begin producing power) within a few minutes. Other
types of powerplants such as nuclear and fossil fuels often take several
hours, at which point the peak demand has often passed. This ability to
virtually produce power on demand during peak periods helps to reduce
energy shortages (especially during the summer months) and makes
hydropower, and the Hartwell Powerplant, an exceptional resource.
The original four generators were designed with a nameplate rating of
66,000 kW. In other words, under controlled conditions, each unit could
produce up to 66,000 kW of electricity per hour (the latter installed
5th unit has a nameplate rating of 80,000 kW). However, the nameplate
rating of the first four
generators recently increased due to a “rehabilitation” or overhaul. The rehab increased the overall plant
capacity from 344,000 kW to 422,000 kW, a 22.7% increase; this is
equivalent to adding a 6th generator.
On average, the Hartwell Powerplant produces over 468 million-kilowatt
hours per year. Revenues during 2001 totaled over $14 million and have
exceeded $330 million since 1962.
How Hydropower Works
Hydroelectric power is produced when water from Hartwell
Lake flows through the intake section of the dam by large pipes called
“penstocks”. The penstocks are located approximately 100 ft. below the
surface of the reservoir. Water flows through these 24 ft. in diameter
penstocks at a rate of 2 – 3 million gallons per minute when generating.
The force of the water rotates the “turbines” which resemble large water
wheels or fan blades.
The rotating turbine causes the 41-inch diameter generator shaft to
spin, which then causes the rotor to turn (the rotor is a series of
magnets where the magnetic field is created). The rotor turns inside the
“stator” – a stationary part of the generator made of copper coils of
wire called “windings”. Electricity is produced as the rotor spins past
(inside of) these windings.
The generators create electricity in the form of volts. By means of
transformers, the electric current produced is “stepped up” or increased
in voltage from 13,800 volts to 230,000 volts for transmission to power
companies or decreased in voltage for use in powerplant operations.
Water used in generating the power is discharged into the river below
the dam, where it can be “reused” for additional purposes such as water
supply and water quality needs of the Savannah River Basin.
Where Does the Power Go?
Power produced at Hartwell and all other Corps operated
powerplants in the southeast, is marketed by the Department of Energy’s
Southeastern Power Administration (SEPA). Power is sold through SEPA to
private power companies and public cooperatives in the Southeastern U.S.
and from there to customers of those companies. Although electricity is
not sold directly to the consumer, the underlying goal of all Corps
hydroelectric projects is to provide power to consumers at the lowest
possible rates. Rates are set by the marketing agency and approved by
the Federal Energy Regulatory Commission. Revenue from Corps powerplants
is returned to the U.S. Treasury.
Top of Page
|
Hartwell Powerplant Rehabilitation
The life span of the Hartwell Powerplant’s four original
generators was expected to be approximately 30 years. So, after 37
years of service, the four original generators underwent a
”rehabilitation” (rehab), or overhaul. Each of the four generators had
over 60,000 hours of operating time; this is equivalent to an automobile
having over 2,700,000 miles on it (if an automobile averaged 45 mph).
Phase I of the rehab
work got underway in 1997. There were three major components of the
rehab work - generator rewinding/turbine refurbishment, replacing and
upgrading circuit breakers, and replacing and upgrading the transformers
(this included installation of an oil/water separator). Phase II
included more equipment such as replacing all of the switchyard breakers
and buswork and updating the powerhouse and Clemson Pumping Station.
Preparations
The Gantry crane seen
here is a permanent part
of the dam and is used to move generator parts from the outside deck
into a workspace within the powerplant. Before the rehab began, a
stress test was performed on the crane because it would be needed to
lift and move the rotors that weigh approximately 300 tons (the rotor is
the heaviest part of each generator). To do this, water was placed in
large balloons to a weight of 375 tons.
Generator Rewind & Turbine Refurbishment
The generator rewind involved stator coil replacements.
Coils are the wound wire components in a generator that produce
electricity when a magnetic field is passed across them (this is what
the rotor spins inside of).
Due to technological advancements, the new coils can be
rated at a higher power output and the generators were upgraded to 129%
of their original ratings.
Turbine refurbishment
consisted of repairing turbine blades. Over the years, water to blade
contact results in very small nicks and general wear to the turbine
blades (referred to as “cavitation”). Old paint was sandblasted and
blades were welded, sanded, and repainted.
In addition to the
refurbishment, “hub-baffles” were added to the turbines. Hub baffles
are devices designed to pull air into the water flowing through the
turbines – this increases dissolved oxygen downstream water and improves
water quality conditions for fish.
Replacing and
Upgrading Circuit Breakers
The circuit breaker
upgrade involved replacing existing air circuit breakers with gas
breakers. Gas breakers are more efficient and have a longer life span.
Air breakers required bi-annual maintenance, while the new gas breakers
only require maintenance every 10 years. Repair work is easier and less
expensive. Additionally, the new circuit breakers have a higher current
rating to handle the higher output of the generators.
Replacing and
Upgrading the Transformers
Transformers have been
replaced to handle the additional increase in power being generated.
Instead of two banks of three, single-phase transformers, there are now
two three-phase transformers (one transformer for units 1 & 2 and one
transformer for units 3 & 4; unit 5 has its own transformer). Each new
transformer, weighing in at over 242,000 lb. (or over 121 tons) and 32.5
ft. long by 21’ wide, was transported (on separate occasions) by train
from St. Louis to the Airline community of Hart County, where it was
then placed on a specially designed flatbed trailer and brought to the
powerplant.
Each transformer
requires between 6,000 to 10,000 gallons of insulating oil. As part of
the transformer work, an oil/water separator was installed. An oil/
water separator is a secondary containment feature that will prevent oil
from entering into the river should a spill occur in relation to the
transformer. It is basically an underground holding area, should a
spill occur, oil would enter into the holding area where it could then
be pumped and properly disposed of.
Conclusion
This diagram gives you
a good idea of the location of the major rehab components in relation to
one another.
The rehab has
resulted in a 29.5% capacity increase each for units 1 - 4, or a 22.7%
increase in plant capacity. (Capacity is the amount of electricity a
generator plant can produce). In other words, due to the increased
nameplate rating, we can produce 22.7% more power than before the
rehab. The rehab has increased the nameplate rating of 66,000 kW to
85,500 kW. This is equivalent to adding a 6th generator. The rehab is
also expected to extend the life of the generators by 35 years. The
Corps continues to provide clean energy as the nation’s power demands
continue to grow.
Top of Page
|
Downstream Safety
The production of hydropower at the powerplant is
accompanied by a rise in the level of the river below the dam, as water
used to drive the generators is discharged into the river. Air horns
located on the top of the dam will sound for one minute before water is
released into the river. The horns are to alert fishermen and other
visitors who might be on the rocks in the riverbed that the river will
soon rise and that they must immediately move to the riverbank. For
safety’s sake, fishermen are encouraged to fish from the riverbank or
from the fishing piers that have been provided.
Top of Page
|
|
Flood Control
Normally, water released from the reservoir passes
through the dam and into the river below by way of the powerplant.
However, there are times when it is necessary to pass substantial
quantities of water downstream quickly for flood control purposes. The
spillway, located on top of the dam, contains 12 large gates, each 40
ft. by 35.5 ft., for the quick release of water from the lake. Water can
be released at the rate of 5.8 million gallons* per minute with all
floodgates open one foot (gates can be opened to five feet or more).
The concrete bucket at the toe of the spillway deflects the flow upward
to dissipate its destructive energy and prevent erosion of the
foundation. The training walls of the concrete structure at each end of
the spillway direct the flow into the river channel below the dam. Water
released through the floodgates cannot be used to generate electricity.
The floodgates at Hartwell Dam have been opened three times for flood
control purposes – in 1964, 1965, and 1994. The three Corps managed dams
and lakes on the Savannah River have prevented over $40 million in flood
damages since 1954.
*Figure based on lake elevation of 660 ft. msl.
Clemson Diversion Dams
In addition to the main dam, two diversion dams were constructed from
1960 - 1961 to divert the flow of the Seneca River around Clemson
University, preventing inundation of a large portion of Clemson property
that was developed before the lake was created.
The construction of the diversion dams created an interior drainage area
of 1,659 acres with 125 acres being the Clemson bottoms or levied area.
This required the construction of a pumping station to remove the water
from this area and to control the elevation between 610’ and 614’. Water
flowing into the basin comes from several sources:
- Hunnicut Creek - a free flowing natural stream.
- Old Seneca River Channel - several springs supply water to this
channel.
- Upper and Lower Diversion Dams - these have a continuous flow of
seepage from the reservoir into the pumping station basin.
- Storm water - from local rains.
The pumping station is equipped with two 40 HP vertical turbine electric
pumps, with a pumping capacity of 2,000 gallons per minute (each). Under
normal weather conditions with little or no rainfall, these two electric
pumps will maintain the specified water level elevations of 610’ to
614’. The two emergency pumps are 30 ft. in diameter vertical turbine
type pumps, with a capacity of 23,500 gallons per minute each. They are
powered by D-398 caterpillar engines rated at 660 HP each.
Top of Page
|
|
Historical Photos Library
Link to:
Historical Photos
|
Facts and Figures
-
When the reservoir is at full summer pool (elevation 660
ft. msl), it covers nearly 56,000 acres. Approximately 24,000 acres of
public land surrounds the lake. The lake has 962 miles of shoreline.
-
The generator rotors, which are turned by the turbines,
are 30 feet in diameter and weigh 300 tons each. They are the heaviest
part of a generator unit.
-
The penstocks are 214 ft. long, made of boilerplate
steel, and are 24 ft. in diameter. Water flows through the penstocks at
a rate of 2 – 3 million gallons per minute.
-
It takes 138,000 gallons of insulating and lubricating
oil to operate the generators. The oil is continuously recycled inside
the powerplant, saving millions of dollars each year.
-
Hartwell Dam is built of more than 880,000 cubic yards of
concrete and more than 3 million pounds of reinforcing steel.
-
The depth of the lake behind the dam is approximately 180
feet.
-
The top of the dam is 204 feet above the Savannah River
Bed.
LOCATION:
89 miles above Augusta
67 miles above Thurmond Dam
7.1 miles below confluence of Seneca and Tugaloo Rivers
DRAINAGE BASIN AREAS:
above mouth of Savannah River 10,579 sq mi
above Augusta, GA 7,508 sq mi
above Hartwell Dam 2,088 sq mi
RESERVOIR:
Top of Power Pool 660 ft-msl 2,549,600 Ac-Ft 55,950 Acres
Top of Flood Control Pool 665 ft-msl 2,842,700 Ac-Ft
Top of Dam 679 ft-msl
Conservation Pool 1,415,500 Ac-Ft 461,170 Million Gal
(461,170,000,000)
Flood Control Pool 293,100 Ac-Ft 95,492 Million Gal
(95,492,000,000)
Water Supply Available (50000 Ac-Ft/1,415,000)*3117 cfs =
110.14 cfs =
71.18 MGD
DAM LENGTHS:
Concrete Section 1,900 ft
Earth Embankments & Saddle Dike 17,852 ft
SPILLWAY:
Type: Concrete Gravity
Gross Length 568.00 ft
Clear Opening Length 480.00 ft
Tainter Gates 12, 40' X 35.5'
Type of Bucket Flip
Radius of Bucket 30.00 ft
Powerhouse Length 340.00 ft
QUANTITIES:
Concrete 975,100 cu-yd
Compacted Fill 4,342,300 cu-yd
Excavation Borrow 5,251,600 cu-yd
Excavation Common 93,900 cu-yd
Excavation Rock 244,200 cu-yd
Rock Toe 33,100 cu-yd
Riprap and Filter 168,400 cu-yd
HYDROPOWER:
Number 5 units
Diameter 24.0 ft
Spacing 68.0 ft
Max Velocity 15.25 ft/sec
GENERATORS:
Installed Capacity 4 Units at 85 MW 1 Unit at 80 MW
Gross Static Head 192 ft
Average Head 171 ft
Minimum Head 142 ft
Generator Bay Floor Elev. 516.0 ft-msl
Turbine Axis 484.0 ft-msl
Top of Page
|
Abbreviations & Glossary
|
Acre-foot (AF) |
The volume of
water require to over one acre to a depth of one foot. 1 acre-foot= 43,560 cubic feet or 326,000 gallons. |
|
Capacity |
The load for
which a generator, turbine, transformer, transmission circuit,
apparatus, station or system is rated. Capacity is also used
synonymously with capacity. |
|
Circuit Breaker |
Any switching device
that is capable of closing or interrupting an electrical circuit. |
|
Confluence |
The combining of two
streams. |
Conservation
Pool |
Usable storage in
reservoir for hydropower, recreation, water quality, fish and
wildlife management, navigation, and water supply purposes,
designed to be filled during normal and high flow periods for use
during low flow periods. |
Cubic Feet per
Second (cfs) |
1cfs=450
gallons per minute (gpm) |
|
Demand |
The rate of
water flow through, over, or around water control facilities. The
rate of flow is measured by stream gage or calculated from
predetermined rating tables. The term may be applied to the rate
of flow from each individual source (such as a particular turbine)
or to be algebraic summation from all individual sources (which
would be the total rate of flow). Total discharge is synonymous
with outflow. |
|
Discharge |
The rate of water
flow through, over, or around water control facilities. The rate
of flow is measured by stream gage or calculated from
predetermined rating tables. The term may be applied to the rate
of flow from each individual source (such as a particular turbine)
or to be algebraic summation from all individual sources (which
would be the total rate of flow). Total discharge is synonymous
with outflow. |
|
Drawdown |
The distance that
the water surface elevation of a storage reservoir is lowered from
a given or starting elevation as a result of the withdrawal of
water to meet some project purpose(s) such as power generation or
creating flood control space. |
Drought
Contingency
Plan |
Detailed drought management plan that addresses current water
conditions in the Savannah River Basin, and serves as a baseline
for future |
Drought
Indicators |
Mechanisms which reflect drought conditions
and severity. Drought indicators consist of hydrologic indicators
such as streamflow, rainfall, reservoir storage levels and
groundwater levels, meteorological indicators such as rainfall,
and human activity indicators, which include navigation cutbacks
and reduction in hydropower generation. |
Drought
Response |
A response network consists of trigger levels
and appropriate management action. Triggers are predetermined
standards reflecting drought intensity which induce responses. |
|
Effluent |
Waste material
discharges into the environment. |
Flood Control
Pool |
Storage above the conservation pool elevation
designed to store floodwater and reduce flooding downstream. |
|
Flow |
The amount of
water passing a given point within a given period of time. |
|
Forebay |
The impoundment immediately above a dam or
hydroelectric plant intake structure. The term is applicable to
all types of hydroelectric developments (e.g. storage,
run-of-river, and pumped-storage).
|
|
Generating Unit |
A single power producing unit,
comprised of a turbine, generator, and related equipment. |
|
Generation |
The act or process of producing
electricity from other forms of energy. Also, the amount of
electric energy so produced. |
|
Generator |
The electrical equipment in
power systems that converts mechanical energy to electrical
energy. |
|
Governor |
The device which measures and
regulates turbine speed by controlling wicket gate angle to adjust
water flow to the turbine. |
|
Guide Curve |
(also Rule Curve or Target Pool Levels).
Guides established to regulate and manage optimum pool elevations
for yearly operations at impoundments. Rule curves can be
designed to regulate storage for flood control, hydropower
production, and other operating objectives, as well as a
combination of objectives. |
Hydroelectric
Plant |
An electric power plant that
uses water to generate power. |
Hydropower
Power |
The energy that is produced
from water. |
|
Impoundment |
A confined
body of water such as a reservoir or lake. Typically created by a
dam to store water that is released to meet to maintain authorized
purposes |
|
Inflow |
The rate of water flow into a reservoir or
forebay during a specified period. |
|
Kilowatt (kW) |
The electric unit of power, which equals
1,000 watts or 1.341 horsepower. |
Kilowatt hour
(kWh) |
Unit for measuring electric energy
consumption or generation over time; it equals one kilowatt of
power applied for one hour of time. A typical home uses about 800
kilowatt hours per month. |
|
Load |
The amount of electric power consumed/delivered at a given point. |
|
Megawatt(mW) |
Unit of electric power, used for measuring
rate of producing or consuming electric energy. One megawatt =
1,000 kilowatts or 1 million watts. A megawatt is equal to 1,341
horsepower. |
Meteorological
Conditions |
Atmospheric phenomena and weather of a region. |
Minimum
Discharge |
The minimum flow that must be released from a
project to meet environmental or other non-power requirements. |
Minimum Pool
Level |
The lowest elevation to which the pool is to be drawn. |
Multi-Purpose
Reservoir |
A reservoir planned to be used for more than one purpose. |
Normal Pool
Level |
The elevation to which the reservoir surface
will rise during ordinary conditions. |
|
Outage |
The period during which a generating unit,
transmission line, or other facility is out of service. |
Peak Demand
Month |
The month or months of highest power demand. |
|
Peaking Plant |
A powerplant which is normally operated to
provide power during maximum load periods. |
|
Penstock |
A conduit carries water from the reservoir to
the turbine in a hydroelectric plant. |
|
pH |
The condition represented by a number, used
to express both acidity and alkalinity on a scale whose values run
from 0 to 14 with 7 representing neutrality, numbers less than 7
increasing acidity. |
|
Powerplant |
A generating station where prime movers (such as turbines),
electric generators, and auxiliary equipment for producing
electricity are located. |
|
Pumped Storage |
A hydropower facility that has reservoir
pumps which also serve as generators, installed in the dam.
During the night, when cheap surplus power is available, the pumps
are run to pump water from a lower reservoir to an upper reservoir
(upstream). During mid-day, when valuable peaking power is
needed, the units are reversed and water is released back to the
lower reservoir to generate electricity. |
|
Releases |
A determined amount of water that is allowed
to pass through or discharged from a dam. |
Reregulation
Structure |
Peaking power plants generally release water
only a few hours per day. A reregulation structure is a smaller
dam located downstream that is capable of storing the intermittent
slugs of water and releasing a continuous flow. |
|
Rule Curve |
Same as “Guide Curve.” |
|
Streamflow |
The rate at which water passes a given point
in a stream, usually expressed in cubic feet per second. |
|
Switchyard |
An assemblage of electrical equipment for the
purpose of tying together two or more electric circuits through
switches, selectively arranged in order to permit a circuit to be
disconnected or to change the electric connection between the
circuits. In a hydroelectric project, the switchyard is the point
at which the energy generated at the project is connected to the
distribution system. |
|
Tailrace |
The area below a dam; the channel that
carries water away from a dam. |
Thermally
Stratify |
During the warm months of the year, the sun
heats the upper layers of the lake. Since the warm water rises,
the surface of the lake continues to warm while the bottom layer
stays cold. During the winter months, the upper layers of the
lake are cooled. The warmer water on the bottom rises, causing
destratification, or “turnover”, of the lake. |
|
Transformer |
An electromagnetic device used to change the
electricity from the generator to usable voltage levels. |
Transmission
Line |
The high voltage lines that
carry electricity from the hydropower plant to the electric
distribution system. |
Triggering
Mechanism |
An indicator that is put in place to indicate
the need to initiate or terminate specific action before a crisis
occurs. At the action levels, the trigger elevation will initiate
a series of actions that will culminate in the reduction of
releases from the projects. |
|
Turbine |
Large blades that are turned by the force of
water pushing against it; is connected to the generator. |
|
Voltage |
The force which
causes the current to flow through an electrical conductor. |
|
Watt |
Basic unit of
electrical power that is produced at one time or rate of doing
work. The rate of energy transfer equivalent to one ampere
flowing under a pressure of one volt at unity power factor. One
horsepower is equivalent to approximately 746 watts. |
|
Wheeling |
The transfer of power and energy from one utility over the
transmission system of a second utility for delivery to a third
utility, or to a load of the first utility. |
|
Wicket Gates |
Adjustable vanes that control the amount of
water that can enter the turbine. |
ABBREVIATIONS
|
|
AF |
acre-feet |
|
cfs |
cubic feet per second |
|
cu |
cubic |
|
ft |
foot, feet |
|
gal |
gallons |
|
gph |
gallons per hour |
|
gpm |
gallons per minute |
|
km |
kilometer |
|
kv |
kilovolt |
|
kva |
kilovolt-amperes |
|
kWh |
kilowatts per hour |
|
m |
meter |
|
mgd |
million gallons per
day |
|
mi |
mile |
|
MWH |
Megawatts per hour |
|
MSA |
Metropolitan
Statistical Area |
|
NGVD |
National Geodetic
Vertical Datum |
|
rpm |
revolutions per
minute |
|
SAD |
South Atlantic
Division |
|
SEPA |
Southeast Power
Administration |
|
sq |
square |
|
WES |
Waterways Experiment
Station |
|
/ |
per |
|
CONVERSION FACTORS |
|
Length
1 mi = 5,280 ft = 1.609 km
1 km = 0.6214 mi = 3,281 ft
Area
1 sq mi = 640 acres = 2.590 sq km
1 acre = 43,560 sq ft = 4,047 sq m
Volume
1 AF = 325,872 gal = 1,233 cu m
1 AF = 43,560 cu ft = 1,613 cu yd
1 cfs-day = 1.983 AF
1 cubic foot = 7.48 gallons = 0.0283 cubic
meters
1 cfs-day = 1.983 AF
1 cubic meter = 35.51 cubic feet
Discharge Rate
1 cu m/sec = 15,850 gpm = 70.04 acre-ft/day
1 cfs = 2,228 gpm = 0.646317 mgd = 1.983
AF/day
1 AF/day = 226.3 gpm = 0.5042 cfs
1 gpm = 8.0208 cu ft/hr
1 cubic foot per second
(cfs) = 448.83
gallons per minute
(gpm) =
0.646 million gallons per day
(mgd) =
0.0283 cubic meters per second (cms)
Energy
1 kilowatt
–hour (kWh) = 3,413 BTU [i]
1 kilowatt
(kW) = 1,000 watts
= 1.341 horsepower
= 56.88 BTU/minute
= 737.56
ft-lbs/second
1 megawatt (MW) = 1,000 kilowatts
= 1 million watts
1 gigawatt (gW) = 1,000 megawatts
Energy Equivalents
1 barrel of
oil (42 gallons)
= 470 kWh at 27% efficiency [i]
= 520 kWh
at 30 % efficiency
= 660 kWh
at 38% efficiency [iii]
1 ton of coal = 2,500 kWh at 37% efficiency
[iv]
1,000 cubic feet of natural gas = 59 kWh at 27% efficiency
[ii]
=
83 kWh at 38% efficiency [iii]
[i] 1 BTU (British Thermal Unit) is the
amount of energy required to raise the temperature of one
pound of water one degree Fahrenheit.
[ii] Typical efficiency for a combustion
turbine.
[iii]
Typical efficiency for new oil- or gas-fired base load steam
plant or combined cycle plant.
[iv] Typical efficiency for a new base load
coal-fired steam plant.
|
|
Interesting Hydropower Links
|
|