INSTALLATION:  FORT GORDON, GA

PROGRAM SUMMARY

Under CONSTRUCTION
9 Projects @ $360M

FY-23 MILITARY CONSTRUCTION PROGRAM
1 PROJECTS @ $22M

FY-24 MILITARY CONSTRUCTION PROGRAM
1 PROJECTS @ $163M

FY-25 MILITARY CONSTRUCTION PROGRAM
1 PROJECTS @ $108M

 

FY23 MILITARY CONSTRUCTION PROGRAM

Project Number

Description

Programmed Amount

97292

Child Development Center

$22,000,000

 

FY24 MILITARY CONSTRUCTION PROGRAM 

Project Number

Description

Programmed Amount

88726

Secret Cyber & DoD Information Network Training Facility

$163,000,000


FY25 MILITARY CONSTRUCTION PROGRAM

Project Number

Description

Programmed Amount

88727

Secret Auditorium and Faculty Operations Facility

$108,000,000

  

 

MILITARY CONSTRUCTION PROJECTS UNDER CONSTRUCTION

Project Number

Description

Contract Amount

Contract Completion Date

76934

Blood Donor Clinic (BOD Sept 21)

$10,391,910

Sep 21

85794 Company Operations Facility $14,776,597 May 22
70677 Access Control Point (BOD Oct 21) $33,157,267 Sep 21
86479 Automation-Aided Instructional Building (BOD Mar 21) $13,033,034 Apr 21
92022 Battle Lab Annex
(BOD May 22)
$2,456,661 Mar 22
88724 SCI Training, Research, & Network Center $99,021,626 Nov 23
88725 SCI Mission Command, University Registrar Force Mod & Proponency Facility $113,494,044 Jul 24
87205 Family Housing New Construction (BOD Dec 22) $10,984,391 Dec 22
55516 AIT Barracks Complex Ph 3 $62,300,766 Nov 23