Restoration Advisory Board (RAB) Public Interest Survey - Tuesday, November 5, 2024

Please click here to access the survey. All submissions must be received by December 4, 2024.

 

Buxton Naval Facility

The Buxton Naval Facility Formerly Used Defense Sites (FUDS) property was used by the U.S. Navy as a submarine monitoring station. The Department of Defense (DoD) acquired the 49.99-acre property on 9 February 1956 through a special use permit with the National Park Service (NPS) and subsequently eight additional acres from private parties for the facility. The Buxton Naval Facility continued to operate until closure on 30 June 1982. The U.S. Coast Guard (USCG) subsequently used the property until 2010, at which point it was returned to NPS.

The Buxton Naval Facility FUDS property contains three projects. Below is a summary of each project:

  • Project 01: On 1 February 1989, the U.S. Army Corps of Engineers (USACE), Savannah District created Project 01 to remove seven aboveground storage tanks (ASTs) (six 1,000-gallon tanks and one 57.6’ x 14’ tank), followed by environmental testing and sampling to determine the need for further action. In 1991, three additional ASTs (one 3,000 gallon, one 4,000 gallon, and one 7,000 gallon tank) were removed from the property. USACE determined no further action was required on 30 September 1993 and the project was closed out on 30 September 2009. The North Carolina Department of Environment and Natural Resources (NCDENR), currently known as the Department of Environmental Quality (NCDEQ), concurred with closeout of the project. Project 01 was reopened on 01 May 2024 to remove a pipe with an odor of petroleum suspected of being part of a fuel distribution system.
  • Project 02: On 17 May 1991, the USACE created Project 02 to demolish and remove a communications tower. However, NPS and USCG informed USACE that the tower was still being used. Accordingly, no demolition or removal activities occurred and USACE closed out the project on 30 September 1991.
  • Project 03: On 20 August 1998, USACE created Project 03 to address soil contamination discovered at the grease ramp/oil change ramp (OCR), Building 9, and underground piping after the USCG’s removal of 27 underground storage tanks (USTs). 
    • Under Project 03, USACE prepared a Comprehensive Site Assessment (CSA) Report in February 2001. The assessment field work included the installation of 10 groundwater monitoring wells, and the collection of soil, groundwater, surface water, and sediment samples for laboratory analysis. In March 2000, during the field work, a fuel oil pipeline connecting an AST and Building 9 were removed and closure sampling revealed soil and grease contamination in the soil. Six additional monitoring wells were installed, and additional sampling was conducted. Naphthalene was detected above NCDENR standards in one groundwater well.
    • In December 2001, the USACE prepared a Corrective Action Plan (CAP). The investigation focused on the former AST pad near Building 7, Building 9, the OCR between Buildings 6 and 7, and Building 19. The CAP recommended the installation of 2 new groundwater monitoring wells near the OCR, demolition and removal of the concrete OCR structure, remediation of soil by excavation and thermal treatment, and monitored natural attenuation of groundwater.
    • In 2004, the USACE removed approximately 4,006 tons (2,706 cubic yards) of contaminated soil, demolished and removed the OCR, collected 30 confirmation samples, and documented this action in a January 2005 report.  Excavations were typically to a depth of seven feet below ground surface (bgs) and confirmation sampling confirmed all contaminated soil had been removed with the exception of one sample due to the presence of critical utilities and an existing road. The contaminated soil was taken to an approved land farm in Martin County, NC.
    • Since 2005, the USACE has performed 32 groundwater monitoring events to evaluate groundwater contaminant concentrations. The most recent event occurred in March 2024. The USACE also conducted groundwater injection treatment with two events in 2020 and 2021. Groundwater monitoring data indicates the injection events have been successful as petroleum contaminant concentrations in the groundwater have decreased significantly. Preliminary data from the March 2024 groundwater sampling event indicate the concentrations of all petroleum constituents are below North Carolina groundwater quality standards.

Project Update

                                                                                                                               

Approximate Cumulative Removal Quantities (as of 12/03/24)

Petroleum-impacted soil (cubic yards)

Petroleum-impacted Water

(gallons)

Concrete

(pounds)

Pipe

(feet)

Metallic debris, cable/wire

(feet)

3,426

61,526

278,000

1,153

1,088

 

 

Frequently Asked Questions

Collapse All Expand All
Expand List item 35705Collapse List item 35705  Q: What is the Corps’ authority to clean up Formerly Used Defense Sites?

A: Congress established the Defense Environmental Restoration Program (DERP) on 17 October 1986 with passage of Section 211 of the Superfund Amendments and Reauthorization Act (SARA). The DERP includes several different programs, one of which is the Formerly Used Defense Sites (FUDS) Program. The Department of Defense (DOD) tasked the U.S. Army with carrying out the FUDS program and execution of the program was delegated to USACE. FUDS restoration efforts are restricted to cleaning up properties formerly owned by, leased to, or otherwise possessed, by the Unites States and transferred outside DOD control prior to October 1986.

For more information about DERP, click on the following link:

https://www.denix.osd.mil/derp/about/

For more information about the FUDS Program, click on the following link:

https://www.usace.army.mil/Missions/Environmental/Formerly-Used-Defense-Sites/

Expand List item 35706Collapse List item 35706  Q: What environmental restoration activities has USACE performed at the Buxton Naval Facility FUDS Property prior to 2023?

A: USACE has performed significant environmental restoration actions within the Buxton Naval Facility FUDS Property. The Buxton Naval Facility FUDS property projects include:

  • Project 01: Opened to address aboveground storage tank removal in 1989 and 1991.  Reopened May 2024, to include additional work, including the ongoing response action (Phase I and Phase II).
  • Project 02: Opened to demolish a communication tower, but was closed out September 1991, after the tower was determined to be beneficially re-used by the U.S. Coast Guard.
  • Project 03: Opened to address soil contamination identified after underground storage tank removal. USACE removed contaminated soil and infrastructure. Since 2005, USACE has performed groundwater monitoring events to evaluate natural attenuation. Groundwater injection treatment was completed in 2020 and 2021.
Expand List item 35707Collapse List item 35707  Q: What actions did USACE take after indications of petroleum along the beach were first reported in September 2023?

A: From September 2023 to August 2024, reports of petroleum, sheen, and odors at the Cape Hatteras National Seashore FUDS property were sporadic and limited to a three-tenths of a mile section of beach. To identify the potential source, USACE sent teams in September, October, November, and December 2023, as well as February, May and June 2024, to collect soil samples, perform borings, dig test pits, take air samples, excavate soil to investigate the potential presence of a tank, remove a suspect pipe and perform geophysical work, and inspect beach conditions.

Expand List item 35708Collapse List item 35708  Q: What action has USACE taken since September 2024?

A: After a significant erosion event in September 2024, that produced petroleum sheens on the beach, the Savannah District team took immediate action and quickly assessed the situation, developed a two-phase response plan, and effectively initiated the ongoing phased response actions. As part of the first phase, a USACE team arrived on-site on September 11, 2024, to mitigate any petroleum release into the ocean and perform a test pit investigation to better define the extent of petroleum-impacted soil. The team did not identify any active petroleum releases. The second phase is ongoing and involves identifying and removing petroleum-impacted soil in the subsurface and performing confirmatory soil sampling in areas along the beach and dunes. Excavations began on October 2, 2024, and as of November 6, 2024, we have removed approximately 1,442 cubic yards and 24,126 gallons of petroleum-impacted soil and water, as well as approximately 138,400 pounds of concrete, 1,153 feet of pipes and 1,088 feet of metal cables and wires. USACE, in close coordination with the North Carolina Department of Environmental Quality (NCDEQ), will continue to investigate this area to ensure protection of human health and well-being of the community and environment. Imagery of response action work can be viewed on our Flickr account at Savannah Corps Flickr.

Expand List item 35709Collapse List item 35709  Q: Did USACE demolish and remove structures and buildings in the 80s?

A: In 1985, USACE removed two buildings (#40 and #19) and associated structures from the former Buxton Naval Facility FUDS property. The funding and authority were provided in a 1984 Congressional appropriation that provided specific authority to remove “unsafe or unsightly buildings and debris.” USACE found the two buildings and associated structures to be unsightly, not unsafe. These appropriations, which granted narrow authority, have long since expired and are no longer available.

Expand List item 35710Collapse List item 35710  Q: Does USACE have current legal authority to remove the remnant Navy Infrastructure being exposed by erosion?

A: When Congress created the FUDS Program in 1986, building demolition and debris removal work was limited to “unsafe” buildings and structures in such a state when transferred out of DOD control. When the Navy ceased control of the Buxton Naval Facility in 1982, buildings and structures were safe, and the vast majority of the facility was subsequently and beneficially used by the U.S. Coast Guard (USCG). Current unsafe conditions are a result of the remnant Navy infrastructure being exposed by erosion on the beach. These conditions did not exist when the property was transferred from Navy control in 1982. For these reasons, USACE does not have the authority under the FUDS Program to address these conditions. We have relayed this information to The National Park Service, the land manager, so they can pursue an alternative way forward to remove the remnant infrastructure. The limited remnant infrastructure that is being removed by the ongoing response action is incidental to accessing and excavating soils underlying the infrastructure within the subdivided areas along the beach and dunes.

Expand List item 35711Collapse List item 35711  Q: When will the beach be safely reopened?

A: The Cape Hatteras National Seashore is currently under the administrative custody, control, and management of the U.S. National Park Service. USACE does not have control over access to the beach. Questions regarding the beach closure or its management should be directed to the Cape Hatteras National Seashore.

Expand List item 35712Collapse List item 35712  Q: Can you provide more detail regarding the groundwater contamination and how it was determined to be unrelated to observations on the beach?

A: USACE removed petroleum contaminated soil in 2004 and has been remediating the groundwater since 2005. USACE experts injected a product into the groundwater that treats petroleum-related contamination at varying levels. From there, USACE has performed quarterly sampling of groundwater to verify the remaining contamination is decreasing. These sampling events are ongoing. For a while now, the only remaining contamination consisted of low levels of methylnaphthalene in one monitoring well. Methylnaphthalene is a daughter product of petroleum, and the low levels indicated the source was being addressed. As of March 2024, groundwater sampling results indicate that detected concentrations of any petroleum contaminants were below the Environmental Protection Agency Regional Screening Levels and North Carolina 02L Groundwater Standards.

Expand List item 35714Collapse List item 35714  Q: What are the next steps for the site?

A: Following the ongoing response action, we will comprehensively sample soil and groundwater within the project area with the intent to delineate the nature and extent of any petroleum contamination remaining at the FUDS property. USACE anticipates contract award to occur in November 2024.

Expand List item 36975Collapse List item 36975  Q: The U.S. Coast Guard’s Site Inspection Report identified elevated lead in the soil and groundwater at the Former Firing Range. What actions are being taken to address lead in the soil and groundwater?

A: A U.S. Coast Guard (USCG) Site Inspection Report identified elevated lead in the soil and groundwater at the former Firing Range area. The Buxton Naval Facility FUDS property currently does not have an open project that covers the Small Arms Range. In anticipation of creating a new environmental restoration project, we are currently gathering information, including the USCG Site Investigation Report, about the Small Arms Range to prepare a project eligibility recommendation. Project approval is required for environmental restoration activities to occur.

Expand List item 35713Collapse List item 35713  Q: When will the beach be safely reopened?

A: In February 2024, the USACE was notified of a pipe that had recently been exposed by erosion and was reported to be emitting a petroleum odor. The pipe was suspected to be historically connected to a fuel distribution system. To further investigate whether the pipe was a potential source of petroleum, the USACE team hired a contractor to remove the pipe and perform confirmatory sampling around the pipe to determine if it was a possible source of contamination. During the week of May 13, 2024, the USACE team removed between 70-80 feet of pipe and 8.54 tons of soil. Additionally, an anomaly, detected via geophysical methods, located north of the pipe was investigated to determine if it was linked to the pipe. The excavation of the anomaly uncovered remnants of an underground storage tank previously removed but did not show signs of contamination and was not connected to the pipe. USACE prepared a draft report to document the results of the pipe removal and soil sampling effort. The draft report is currently being reviewed by agency stakeholders and it will be released to the public when the report is finalized. The results reinforce USACE’s plan to conduct comprehensive sampling over a wider area of the FUDS property to fully delineate the petroleum contamination remaining in the soil and groundwaterA: The Cape Hatteras National Seashore is currently under the administrative custody, control, and management of the U.S. National Park Service. USACE does not have control over access to the beach. Questions regarding the beach closure or its management should be directed to the Cape Hatteras National Seashore.

Expand List item 36976Collapse List item 36976  Q: Is a Restoration Advisory Board (RAB) being considered for this property?

A: A RAB is a stakeholder advisory group that meets regularly to discuss environmental restoration at DOD sites, such as the Buxton Naval Facility FUDS property. A RAB is not a decision-making body but rather an opportunity for interested community members to be involved in the environmental restoration process and influence the cleanup decisions through discussions of ideas, concerns, questions, and the chance to provide direct input/feedback to the DOD entity and regulatory agencies. A RAB is a formal process and may only address issues with environmental restoration activities. During a public meeting held on November 4, 2024, USACE, Savannah District invited the public to take a survey to gauge the community’s interest in establishing a RAB. The public interest survey is available until December 4, 2024, and can be accessed through the following link https://www.surveymonkey.com/r/BuxtonPublicInterestSurvey until December 4, 2024.

News Releases

Buxton FUDS restoration advisory board survey results
12/10/2024
SAVANNAH, Ga. – The U.S. Army Corps of Engineers, Savannah District, is in the process of documenting its determination to establish a restoration advisory board, based on survey responses from the...
Survey available for Buxton FUDS Restoration Advisory Board--work continues
11/12/2024
SAVANNAH, Ga. – During a public meeting at the Fessenden Center in Buxton, North Carolina, Nov. 4, 2024, the U.S. Army Corps of Engineers, Savannah District, invited the attendees to take a survey to...
Buxton FUDS public meeting Nov. 4 at Fessenden Center - on-site excavations continue
11/1/2024
SAVANNAH, Ga. – As a reminder, the U.S. Army Corps of Engineers, Savannah District, will host a public meeting at the Fessenden Center Nov. 4, 2024, from 7 to 9 p.m., to provide information about...
Buxton FUDS public meeting date set – cleanup continues at site
10/18/2024
SAVANNAH, Ga. – The U.S. Army Corps of Engineers, Savannah District, has set the date, time, and location for a public meeting about the Buxton Naval Facility Formerly Used Defense Sites property as...
Response action progressing at Buxton FUDS property in Dare County N.C.
10/9/2024
SAVANNAH, Ga. – Excavation of petroleum-impacted soil continues as part of an ongoing U.S. Army Corps of Engineers, Savannah District phased response action at the Buxton Naval Facility, a Formerly...
Contractor arrives, continues response action at Buxton FUDS property
9/20/2024
BUXTON, N.C. – The company contracted by the U.S. Army Corps of Engineers, Savannah District, arrived today at the former Buxton Naval Facility, a Formerly Used Defense Sites property, located within...
USACE deploys response team, awards contract to address conditions at Buxton Formerly Used Defense Site
9/13/2024
SAVANNAH, Ga. – The U.S. Army Corps of Engineers deployed a team earlier this week to the Former Buxton Naval Facility, a Formerly Used Defense Sites property located within Cape Hatteras National...
USACE to perform response action at Buxton FUDS
9/9/2024
SAVANNAH, Ga. – The U.S. Army Corps of Engineers will deploy a team this week to the Former Buxton Naval Facility, a Formerly Used Defense Site property located within Cape Hatteras National Seashore...
Commander gives latest Buxton FUDS property update at Dare County Meeting
9/6/2024
SAVANNAH, Ga. – During the Dare County Board of Commissioners monthly meeting, Sept. 3, 2024, Col. Ron Sturgeon, U.S. Army Corps of Engineers, Savannah District commander, talked about the latest...
Savannah District Commander to provide Buxton FUDS update
8/2/2024
MANTEO, N.C. – The U.S. Army Corps of Engineers, Savannah District Commander, Col. Ron Sturgeon, is set to provide an update about the Buxton Naval Facility, a Formerly Used Defense Site property...
Corps of Engineers plans for more work at Buxton FUDS property
6/13/2024
SAVANNAH, Ga. – The U.S. Army Corps of Engineers plans to conduct geophysical work to identify any potential fuel distribution components remaining at the Buxton Naval Facility, a Formerly Used...
Buxton FUDS pipe removal work completed, results pending
5/21/2024
SAVANNAH, Ga. – The U.S. Army Corps of Engineers, Savannah District, has completed the pipe removal work at the former Buxton Naval Facility Formerly Used Defense Sites property in Dare County North...
Army Corps of Engineers invites Buxton community to meeting
5/10/2024
SAVANNAH, Ga. – The U.S. Army Corps of Engineers, Savannah District, in coordination with the Dare County Board of Commissioners, would like to invite the Buxton community to a public meeting Tuesday,...
Contract to remove potential source of petroleum awarded ahead of schedule
5/3/2024
SAVANNAH, Ga. – Leadership from the U.S. Army Corps of Engineers, South Atlantic Division and the Savannah District conducted a site visit to Buxton, North Carolina, May 1, 2024, to meet with...
Corps of Engineers completes report on Buxton Beach contamination
3/28/2024
BUXTON, N.C. – The U.S. Army Corps of Engineers, Savannah District, has completed its Summary Report of site visits occurring from September 2023 through February 2024 on a section of shoreline in...
U.S. Army Corps of Engineers Works to Address Petroleum Soil Found Along Shoreline at Buxton
10/23/2023
BUXTON, N.C. (USACE) – The U.S. Army Corps of Engineers, Savannah District, has completed its initial analysis of historical documentation, information gathered during site visits and soil samples...

Contact Information

For questions, please contact us here.

Photos

Workers preparing Buxton site for severe weather

The excavation team at the Buxton Formerly Used Defense Sites Project area place sand bags on the plastic cover to secure stockpiles of sand before the impending severe weather hits the Outer Banks area Nov. 14-17, 2024.  (Photo by Terry Brooks, USACE)

View Additional Photos on Flickr