The Buxton Naval Facility Formerly Used Defense Sites (FUDS) property was used by the U.S. Navy as a submarine monitoring station. The Department of Defense (DoD) acquired the 49.99-acre property on 9 February 1956 through a special use permit with the National Park Service (NPS) and subsequently eight additional acres from private parties for the facility. The Buxton Naval Facility continued to operate until closure on 30 June 1982. The U.S. Coast Guard (USCG) subsequently used the property until 2010, at which point it was returned to NPS.
The Buxton Naval Facility FUDS property contains three projects. Below is a summary of each project:
- Project 01: On 1 February 1989, the U.S. Army Corps of Engineers (USACE), Savannah District created Project 01 to remove seven aboveground storage tanks (ASTs) (six 1,000-gallon tanks and one 57.6’ x 14’ tank), followed by environmental testing and sampling to determine the need for further action. In 1991, three additional ASTs (one 3,000 gallon, one 4,000 gallon, and one 7,000 gallon tank) were removed from the property. USACE determined no further action was required on 30 September 1993 and the project was closed out on 30 September 2009. The North Carolina Department of Environment and Natural Resources (NCDENR), currently known as the Department of Environmental Quality (NCDEQ), concurred with closeout of the project. Project 01 was reopened on 01 May 2024 to remove a pipe with an odor of petroleum suspected of being part of a fuel distribution system.
- Project 02: On 17 May 1991, the USACE created Project 02 to demolish and remove a communications tower. However, NPS and USCG informed USACE that the tower was still being used. Accordingly, no demolition or removal activities occurred and USACE closed out the project on 30 September 1991.
- Project 03: On 20 August 1998, USACE created Project 03 to address soil contamination discovered at the grease ramp/oil change ramp (OCR), Building 9, and underground piping after the USCG’s removal of 27 underground storage tanks (USTs).
- Under Project 03, USACE prepared a Comprehensive Site Assessment (CSA) Report in February 2001. The assessment field work included the installation of 10 groundwater monitoring wells, and the collection of soil, groundwater, surface water, and sediment samples for laboratory analysis. In March 2000, during the field work, a fuel oil pipeline connecting an AST and Building 9 were removed and closure sampling revealed soil and grease contamination in the soil. Six additional monitoring wells were installed, and additional sampling was conducted. Naphthalene was detected above NCDENR standards in one groundwater well.
- In December 2001, the USACE prepared a Corrective Action Plan (CAP). The investigation focused on the former AST pad near Building 7, Building 9, the OCR between Buildings 6 and 7, and Building 19. The CAP recommended the installation of 2 new groundwater monitoring wells near the OCR, demolition and removal of the concrete OCR structure, remediation of soil by excavation and thermal treatment, and monitored natural attenuation of groundwater.
- In 2004, the USACE removed approximately 4,006 tons (2,706 cubic yards) of contaminated soil, demolished and removed the OCR, collected 30 confirmation samples, and documented this action in a January 2005 report. Excavations were typically to a depth of seven feet below ground surface (bgs) and confirmation sampling confirmed all contaminated soil had been removed with the exception of one sample due to the presence of critical utilities and an existing road. The contaminated soil was taken to an approved land farm in Martin County, NC.
- Since 2005, the USACE has performed 32 groundwater monitoring events to evaluate groundwater contaminant concentrations. The most recent event occurred in March 2024. The USACE also conducted groundwater injection treatment with two events in 2020 and 2021. Groundwater monitoring data indicates the injection events have been successful as petroleum contaminant concentrations in the groundwater have decreased significantly. Preliminary data from the March 2024 groundwater sampling event indicate the concentrations of all petroleum constituents are below North Carolina groundwater quality standards.