Savannah Harbor expansion boiled down: 40 miles long, 47 feet deep

U.S. Army Corps of Engineers, Savannah District
Published Aug. 23, 2017
A Spider Barge (right) distributes outer-channel sediment into a barge held in place by a tug boat (left), as a Cutter Head Dredge Alaska (outside frame) pumps material through the pipe. The work is part of the Savannah Harbor Expansion Project. The outer channel will extend up to 20 miles into the Atlantic when complete, making the entire shipping channel 40 miles long from entry to Garden City Terminal.

A Spider Barge (right) distributes outer-channel sediment into a barge held in place by a tug boat (left), as a Cutter Head Dredge Alaska (outside frame) pumps material through the pipe. The work is part of the Savannah Harbor Expansion Project. The outer channel will extend up to 20 miles into the Atlantic when complete, making the entire shipping channel 40 miles long from entry to Garden City Terminal.

Dissolved Oxygen Injection System up-river site at about 30 percent complete.

This is an image of the up-river facility of Dissolved Oxygen Injection System, as part of the Savannah Harbor Expansion Project. This feature will remove water from the river, inject it with oxygen using devices called Speece cones, and return the water back to the river. These devices will maintain the level of dissolved oxygen in the harbor at the pre-SHEP 47’ deepening level. The image here shows the facility at about 30 percent complete.

Raw Water Storage Impoundment (RWSI) approaches 80 percent completion

As shown in this image, approximately 80 percent of the Raw Water Storage Impoundment is complete. The RWSI is part of the environmental mitigation for the Savannah Harbor Expansion Project (SHEP) which will deepen the premier harbor in the state. The RWSI will hold raw water for short-term use by the City of Savannah water department in those rare occasions when low river flows coincide with very high tides pushing natural chlorides near the city's water intakes. The small reservoir will contain approximately two days of water. The extreme high tides last fewer than 12 hours. (U.S. Army Corps of Engineers photo.)

NR 17-30
SAVANNAH, Ga. – It’s arguably one of the most important infrastructure projects in the nation, and a boon for the transportation of goods throughout the southeast. The Savannah Harbor Expansion Project, known as SHEP, will deepen the Savannah Harbor 5 feet, down to 47 feet below mean sea level at low tide. That will enable modern deep-draft cargo vessels, akin to floating islands, to call more easily on the port here. 

According to the U.S. Army Corps of Engineers, deepening the Savannah Harbor just 5 additional feet will yield an economic benefit of $282 million every year for the nation. It is a timely endeavor considering the newly expanded Panama Canal now handles the monolithic Post-Panamax cargo vessels transiting the Pacific Ocean. But going only 5 feet deeper in Savannah is a vastly complex undertaking when the 40-mile channel snakes through one of the most environmentally sensitive estuaries on the east coast. 

The project will cost just shy of a billion dollars at $973 million, according to Spencer Davis, senior project manager for the Corps’ Savannah District. Much of the cost is attributed to the intricate environmental mitigation efforts required to counter the would-be effects in the local estuary. Roughly half the project budget goes to ensuring strong environmental protection and impact mitigation. For perspective, harbor deepening projects in other rivers typically devote around 10 percent of the cost to environmental mitigation.

“SHEP is perhaps one of the most environmentally sensitive civil works projects in the Corps’ portfolio,” said Davis. “Meeting the demands for commerce and environmental stewardship are combined into a single purpose with SHEP.”

Despite the additional costs to remain environmentally accountable, Davis said no other deepening project can compete with SHEP’s return on investment for taxpayers: an astonishing $7.30 return for every dollar spent.

One of the challenges for Davis involves organizing multiple timelines within the project that affect one another. Several of the 11 major construction features are interdependent, and must be meticulously orchestrated for the project to advance.

“Seven of the 11 features were developed to protect the environment and must be complete before we finish the navigation portion of the project,” said Davis.

The navigation portion – the deepening itself -- involves removing 24 million cubic yards of sediments from the riverbed over several years.

“When a project moves that much material out of a waterway, planners need to know exactly how this impacts ecosystems in order to proceed in an environmentally friendly way,” added Davis.

One of the more prominent environmental features is designed to replace dissolved oxygen in the river during hot summer months when oxygen levels are low. According to Tracy Hendren, chief of Savannah District’s hydrologic and hydraulic engineering branch, Speece cone technology will pull large volumes of water into 20-foot-tall cone shaped devices that will dissolve oxygen into the river water. This feature, made up of two facilities at different locations on the river, can inject a total of 40,000 pounds of oxygen a day into the river. This system will maintain oxygen at its pre-deepened levels during hot, dry months, when oxygen depletion occurs.

Another significant environmental feature will re-route the flow of freshwater into the upper portion of the estuary. Engineers will accomplish this with a series of cut closures and channel dredging in certain tributaries, along with construction of a flow diversion structure, according to Beth Williams, SHEP’s lead engineer. The design will mitigate for increasing salinity levels from the deepening, and thereby protect local tidal freshwater wetlands from saltwater intrusion.

These and other environmental features for SHEP have been approved by three other federal agencies, which include the Environmental Protection Agency, the U.S. Fish and Wildlife Service, and the National Oceanic and Atmospheric Administration Fisheries Service.

The Georgia Ports Authority and the Georgia Department of Transportation share the cost of SHEP, Davis said. The federal share covers 75 percent of the cost and the Georgia share covers the remaining 25 percent.

“This project is part of the solution to our nation’s need to improve transportation infrastructure and invigorate the economy,” said Erik Blechinger, deputy district engineer for Planning, Programs and Project Management for the Corps in Savannah. “In the Southeast, the population is expected to increase significantly – more than 25 percent over the next 25 years. With Georgia being central to the southeast, it is one of the ideal places to invest in transportation efficiencies.”

SHEP is currently on schedule with an anticipated completion time of January 2022. It is expected to contribute more than $14 billion to the economy over 50 years.