Savannah Harbor Dredged Material Containment Areas (DMCA), Georgia and South Carolina

PROJECT NAME AND STATESavannah Harbor Dredged Material Containment Areas (DMCA), Georgia and South Carolina

AUTHORIZATION: The DMCAs are included as a part of the Savannah Harbor Federal Navigation Project authorized in the Water Resources Development Act of 1992 (P.L. 102-580).  Section 201 (P.L. 104-303) of the Water Resources Development Act of 1996 addressed cost sharing for dredged material containment areas.

SUMMARIZED FINANCIAL DATA

Construction

Estimated Federal Cost

$73,780,000

Estimated Non-Federal Cost

$39,727,000

Total Estimated Cost

$113,507,000

 

 

Allocation thru FY 2019

$56,250,624

Allocation thru FY 2020

$0

President's Budget for FY 2021 $0

Programmed Balance to Complete After FY 2021

$17,529,376

 

LOCATION AND DESCRIPTION: Navigation.  The Savannah Harbor Dredged Material Containment Areas (DMCAs) are located in Jasper County, SC and Chatham County, GA and are adjacent to the upper 21.3 miles of the Savannah Harbor Federal Navigation project.  The DMCAs are integral to the continued operations and maintenance of the Navigation Project.  The DMCAs project provides for incrementally raising each of the dikes within the Federal project’s seven active DMCAs to increase their capacity as required to support the Savannah Harbor Federal Navigation project.  The increase in DMCA capacity is cost-shared with the State of Georgia under the authority provided in the Water Resources Development Act of 1996.  The Project Cooperation Agreement was executed with the Georgia Department of Transportation in January 2005 for project costs through FY 2025.

ACTIVITIES FOR FY2020The District is continuing to raise the dike and rehabilitate the weirs at DMCA 12A to increase capacity.
             
ACTIVITIES FOR FY2021Continue the DMCA 12A dike raising contract and prepare to close the contract out in FY 21.
                          
ISSUES AND OTHER INFORMATIONThe Georgia Port Authority’s Garden City Terminal is the second largest container port on the US East Coast by container volume, and the fourth largest in the nation.  The Long Term Management Strategy (LTMS) for the Savannah Harbor, dated August 1996, describes the least cost plan to continue maintenance of the existing project as the sequential raising of dikes in each of the DMCAs.  Maintaining adequate disposal capacity is critical to the ability of the U.S. Army Corps of Engineers to operate and maintain the existing Savannah Harbor Federal Navigation project. 

 

MILESTONE SCHEDULE

 DMCA 12A Award Contract                                      13 Sep 2019 (A)

DMCA 12A Dike Raising Physically Complete         18 Dec 2020

 DMCA 12A Fiscally Complete                                   23 Apr 2021


ADMINISTRATION POSITIONThis project is consistent with Administration policy.
 
ACTION OFFICER:  Margarett (Mackie) McIntosh                                25 Mar 2020
                                      CESAS/912-652-5320