INSTALLATION:  FORT BRAGG, NC
         

PROGRAM SUMMARY

UNDER CONSTRUCTION
0 PROJECTS @ $0M
           
FY-19 MILITARY CONSTRUCTION PROGRAM
2 PROJECTS @ $4.15M
         
FY-20 MILITARY CONSTRUCTION PROGRAM
0 PROJECT @ $0M
                    
FY-21 MILITARY CONSTRUCTION PROGRAM
0 PROJECTS @ $0M
             
FY-22 MILITARY CONSTRUCTION PROGRAM
1 PROJECTS @ $12M

FY-23 MILITARY CONSTRUCTION PROGRAM
1 PROJECTS @ $8.3M

 

FY-19 MILITARY CONSTRUCTION PROGRAM

Project Number

Description

Programmed Amount

89132

Phase III Ground Source Heat Pump, Historic District (FY18-scheduled to Award outside FY)

$3,000,000

91164 Upgrade Chiller Plant (Late Insert FY 18-scheduled to award outside FY $1,150,000

 

FY-20 MILITARY CONSTRUCTION PROGRAM

Project Number

Description

Programmed Amount

None

None

NA

 

FY-21 MILITARY CONSTRUCTION PROGRAM

Project Number

Description

Programmed Amount

None

None

NA

 

FY-22 MILITARY CONSTRUCTION PROGRAM

Project Number

Description

Programmed Amount

AM00126

DSO Addition

$12,000,000

 

FY-23 MILITARY CONSTRUCTION PROGRAM

Project Number

Description

Programmed Amount

86262

Infantry Platoon Battle Course

$8,300,000

 

MILITARY CONSTRUCTION PROGRAM – PROJECTS UNDER CONSTRUCTION

Project Number

Description

Contract Amount

Contract Completion Date

None